[Pgi-wg] action list

Johannes Watzl watzl at nm.ifi.lmu.de
Mon Feb 15 08:31:24 CST 2010


-----------------
New actions
-----------------

action (Balasz): upload minutes from the call on 28 Jan.

action (all): go through the wiki and add, correct content

-----------------
Previous actions
-----------------

PENDING

action (all): nail down validation steps in ppt, we have to write it
down and agree on it

action (Aleksander): security aspects for credentials in data staging
will be done by Aleksander

-----------------

-----------------
-----------------

-----------------

COMPLETED
action (Morris): GIN list set of DEMOS and call for more demos

Ilia and Emannouil are in GIN mailinglist now
-----------------

COMPLETED
action (Emmanouil): get in touch with Ilia
------------------

COMPLETED
action (Johannes): ask Nils about the date of the interoperability day
changed to Johannes
try to arrange
GIN1
GIN2
PGI1
--
PGI2
PGI3
PGI not overlapping with GLUE
-----------------

COMPLETED
action (Morris): session proposals -> call for sessions
As we discussed the 3 PGI working sessions should be part of the
interoperability day that was already agreed with the local chair man
(Nils) and therefore I requested no official sessions yet. However, I
contacted Nils to clarify things.
-----------------

COMPLETED
action (Morris): should arrange that someone from gLite is there
-----------------

COMPLETED
action (Morris): check if there is a BES session, discuss with Andrew
-----------------







Am 21.01.2010 17:10, schrieb Johannes Watzl:
> -----------------
> New actions
> -----------------
> 
> action (all): nail down validation steps in ppt, we have to write it
> down and agree on it
> 
> -----------------
> Previous actions
> -----------------
> 
> action (Morris): GIN list set of DEMOS and call for more demos
> 
> Ilia and Emannouil are in GIN mailinglist now
> -----------------
> 
> COMPLETED
> action (Emmanouil): get in touch with Ilia
> ------------------
> 
> action (Johannes): ask Nils about the date of the interoperability day
> changed to Johannes
> try to arrange
> GIN1
> GIN2
> PGI1
> --
> PGI2
> PGI3
> PGI not overlapping with GLUE
> -----------------
> 
> COMPLETED
> action (Morris): session proposals -> call for sessions
> As we discussed the 3 PGI working sessions should be part of the
> interoperability day that was already agreed with the local chair man
> (Nils) and therefore I requested no official sessions yet. However, I
> contacted Nils to clarify things.
> -----------------
> 
> COMPLETED
> action (Morris): should arrange that someone from gLite is there
> -----------------
> 
> COMPLETED
> action (Morris): check if there is a BES session, discuss with Andrew
> -----------------
> 
> action (Aleksander): security aspects for credentials in data staging
> will be done by Aleksander
> -----------------

-- 
        _  _ _  _ _  _          Johannes Watzl
        |\/| |\ | |\/|          Institut für Informatik / Dept. of CS
        |  | | \| |  |          Ludwig-Maximilians-Universität München
     ======= TEAM =======       Oettingenstr. 67, 80538 Munich, Germany
                                Room E 005, Phone +49-89-2180-9162
Munich Network Management Team  Email: watzl at nm.ifi.lmu.de
Münchner Netz-Management Team   http://www.nm.ifi.lmu.de/~watzl


More information about the Pgi-wg mailing list